The conversation

Lessons learnedExperience excerpt · English

I worked with a startup company ~8 years ago that wanted to go after government contracts

… I worked with a startup company ~8 years ago that wanted to go after government contracts. According to the owners, everyone they demo'd the product to said it was very clearly superior to what they were currently using. Unfortunately, the people who would use it are not the people that sign off on paying for it. Those people had checklists of irrelevant requirements, slow response times, almost certainly pressure to select "certain" vendors (i.e. those who threw money into lobbying the right folk). It got to the point where they seriously considered hiring a consulting company whose sole purpose was to help others navigate all the red tape that gets thrown in your way when you try to get government contracts. In the end, they realized that they were better off pivoting entirely to the private sector instead of doing a half and half approach. I seem to recall a similar tale with the lead pipe retrofitting in Flint, MI... contractors to do the job were picked not necessarily by speed and capability, but by other qualities. …

Original discussionWhen did New York start building slowly?241 source comments · at import
5

What was this responding to?

Parent context · original excerpt

KL

Alon Levy and the transit costs project are a great source of actual hard analysis on this- https://pedestrianobservations.com/2023/02/25/the-issue-of-c... has a great concise breakdown, pasted here because no one will click through: Based on around 100 interviews and many diagrams and reports, we managed to decompose the New York construction cost premium over low-cost countries, which is about a full order of magnitude, into the following items: The stations are overbuilt by a factor of 3, which contributes an overall factor of 2 cost premium The systems are not standardized, which contributes a factor of about 2.3 cost premium for the systems and 1.35 overall Labor costs (including supervisors and other white-collar workers) are 50% of hard costs in New York where they should be about 25%, contributing a factor of 3 premium on labor costs and 1.5 overall Procurement problems inclu…

Full original

Community replies 0

No community replies yet. Add your perspective.

Replies from the source 5

Direct replies available in this import. Original-language excerpts.

NI

> the people that sign off on paying for it. Those people had checklists of irrelevant requirements, slow response times, almost certainly pressure to select "certain" vendors This reads like a lack of democratic influence and even direct corruption. That is, these "stakeholders" are not concerned that the voters would be unhappy with their performance, and would fire them (directly or through an action of a newly elected official). They seem to be conveniently shielded from feedback of the population which they nominally are hired to serve.

Full original
ME

> According to the owners, everyone they demo'd the product to said it was very clearly superior to what they were currently using. And owners have never lied about the superiority of their product, or what other people think. Except that is pretty much all they do.

Full original
IN

Eons ago I worked for a startup that sold product to the City/County of San Francisco. We had insiders on staff. A product that management and rank+file loved. We had low hanging fruit just there for the picking. We had experience dealing with other large cities. I predicted SF would inflict doom and gloom before I left, and I did leave before a full scale deployment got underway. But I don't think it'd be fair to lay the entire blame on San Francisco. That said, dealing with San Francisco definitely gummed up the works. Lots of legacy crap, changing requirements, slow moving folks, etc. Dealing with Los Angeles was a walk in the park.

Full original
H2

> the people who would use it are not the people that sign off on paying for it. Reminds me of a demo I did for some Congresscritters once. The staffer said "It'll take $50k per record to bring this database online" so they refused to look at the live, running demo I had of the database online. I heard, later, that someone else got "$50k per record" as a contract.

Full original
AC

> Those people had checklists of irrelevant requirements, slow response times, almost certainly pressure to select "certain" vendors (i.e. those who threw money into lobbying the right folk) That last part isn’t true in my experience, but that makes it harder to solve: every procurement officer I’ve worked with has been very scrupulous about not favoring a vendor but they’re operating under rules for things like fairness and security which are hard to comply with. A huge company can hire a room full of people to document how they’re complying with everything but a startup is going to run into exactly the problem you described. The big guys all support this since it has the effect of limiting options without actually being illegal — who’s going to argue against risk reduction, right?